Monday, April 30, 2012

OIS Bengaluru Campus Site – Weekly Progress(23rd to 28th April)

image

Tennis court toe wall construction is in progress.

image

Swimming pool PCC completed.

image

Ground floor roof slab shuttering is in progress.

image

Plinth beam shuttering is in progress.

 

image

Plinth beam concreting

image

Foot ball ground lawn work completed.

image

Floor PCC is in progress.

image

West side view of GLC block. Shuttering work is in progress.